08/02/05 Startup of Port Washington Generating Station celebrated
08/01/05 We Power gives Full Notice to Proceed to Bechtel for Oak Creek expansion
07/31/05 Top Plant: Port Washington Generating Station
07/19/05 Port Washington Generating Station begins commercial operation
07/01/05 Bechtel commences site activities at Oak Creek
06/28/05 Supreme Court reverses Oak Creek decision
05/18/05 U.S. Army Corps of Engineers issues permit for Oak Creek
03/31/05 DNR reissues water permit for Oak Creek Power Plant, Elm Road Generating Station
03/11/05
Appeal
of Chapter 30 permit dismissed
02/03/05
DNR
air permit for Oak Creek expansion affirmed
01/05/05
Wisconsin
Supreme Court agrees to hear case
12/14/04 We Energies requests Wisconsin Supreme Court take Oak Creek expansion case
12/02/04
We Energies to appeal court decision on Oak
Creek expansion
11/30/04
PSCW to appeal
court decision on Oak Creek expansion
11/29/04
Court
vacates PSCW’s Order for Oak Creek expansion; company reviewing
legal options
11/23/04
Chapter
30 permit issued for Oak Creek Power Plant expansion
09/01/04
Port
Washington Lateral pipeline nears completion
08/18/04 Racine County Approves Conditional Use Permit for Oak Creek Expansion
07/27/04 Caledonia Town Board Unanimously Approves Agreement with We Energies
07/20/04
We Energies, town of Caledonia reach tentative agreement on Oak Creek Power Plant expansion
06/21/04 Public open house at Port Washington Power Plant set for June 27
06/18/04
Final coal delivery at Port Washington Power Plant
06/10/04
Milwaukee
Building and Construction Trades Council and Bechtel Construction Company
Sign Project Labor Agreement for Oak Creek Expansion
01/14/04
DNR
issues air permit for new Oak Creek units
2001-2003 News Releases
|